Right of Way (ROW) Challenge in Construction of Transmission Lines & its Mitigation in India

Mar 17, 2023Mar 17, 2023

At COP26 summit in Glasgow in Nov’2021, India has pledged 500 GW of non-fossil fuel based installed capacity by the year 2030 and agreed to meet 50% of its energy requirement by renewable sources.

December 30, 2022. By News Bureau

Ultimate Goal of Financing Solar Rooftop Projects is to Promote Sustainable Energy Sources

Promoting Clean Technology and Sustainability in All Operations

Renewable energy is the future of power in the entire world

Grew Energy Among Successful Bidders for Solar Module PLI Tranche II

Businesses can reap economic and environmental benefits by investing in solar power

Guide online Free signup Advertise my Company A) Right of Way Corridor - Statutory Provisions B) Transmission Lines Construction Phase ROW Issues - MOP Guidelines C) Right of Way (ROW) Hurdles in O&M Stage of Transmission Lines:- D)Factors Contributing to ROW :- E) Approaches for Reducing ROW by Adapting New Innovative Technologies : - F) Mitigation of ROW Conclusion :-